Development Planning 20.10. - 31.10.
Revision as of 09:52, 28 October 2025 by Davorciric (talk | contribs)
Team availability
This map holds the ZUGSEIL product development team and its planned availability during the upcoming days. If anything changes to this availability, please notify the line and the product manager as soon as possible.
| Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Function | 20.10. | 21.10. | 22.10. | 23.10. | 24.10. | 27.10. | 28.10. | 29.10. | 30.10. | 31.10. | 03.11. | 04.11. | 05.11. | 06.11. | 07.11 | 10.11. | 11.11. | 12.11. | 13.11. | 14.11. |
| Stefan Seiler | Product Owner | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ |
| Rene Schneider | Process Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Christiane Hornemann | UI Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Dennis Huesemann | Server administrator | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Davor Ciric | Senior Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Tijana Bezbradica | Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ✅ |
| Ilija Bubanj | Quality Engineer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Luka Grbic | Support / QA | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Nikola Kerkez | Backend Developer | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Petar Ilic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Aleksandar Lazic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ |
| Zivko Rankovic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ✅ |
| Ivan Juras | Backend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ✅ |
| Nataša Lukić | Backend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ✅ |
| Nebojsa Trajkovic | B-Op developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| 👨💻 DEV assignments | 20.10. - 24.10. | 27.10. - 31.10. | |
|---|---|---|---|
| Nikola Kerkez | BE | Sick 3 days, 2 days worked | Catalog hub |
| Ivan Juras | BE | Hypercare | Hypercare |
| Nataša Lukić | BE | Design Studio process extensions for approvals | Support(catalog script for Luka), SLH |
| Aleksandar Lazic | FE | Hypercare | Hypercare |
| Živko Rankovic | FE | Catalog hub | Catalog hub |
| Petar Ilic | FE | Design Studio process extensions for approvals | Misc, Shop |
Regular vacation requests are applied to over this page, please.
| TOPIC/Project
Task creation |
WBS / Project / Task | FE
BE |
01.09.-05.09. | 08.09.-12.09. | 15.09.-19.09. | 11.09.-26.09. | 29.09.-03.10. | 06.10.-10.10. | 13.10.-17.10. | 20.10.-24.10. | 27.10.-31.10. | Promises / Customer Info / Comments | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Appointments (responsive) | FE | Last minute POS extensions for Appointments | Done | Refactoring - moving to new architecture | |||||||||
| BE | Done | ||||||||||||
| Regular Shop refactorization | FE | 20% | 20% | same what we did for Context based ordering, needs to be done for Regular (speed optimization) | |||||||||
| BE | 20% | 20% | |||||||||||
| PSA extensions for GoLive | FE | Done | First round delivered in time, then came feedback and forgotten features. | ||||||||||
| BE | Done | ||||||||||||
| SBB support integration (Klesy/BKL) | FE | Done | Support and feedback resolving | ||||||||||
| BE | Done | ||||||||||||
| SLH | |||||||||||||
| CBO refactoring | |||||||||||||
| 🚀 SBB HYPERCARE (after GoLive) | FE | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Phase that comes after GoLive | |||
| BE | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | |||||
| Design Studio extensions (for material and financial approvals) | FE | 30% | 100% | Done | Design Studio, Orders overview/details, Pending tasks app | ||||||||
| BE | 30% | 100% | Done | ||||||||||
| Catalog Designer (Catalog HUB) | FE | 10% | 30% | 60% | 80% | 80% | Paused because of SBB GoLive responsive | ||||||
| BE | 10% | 30% | 60% | 80% | 80% | ||||||||
| Catalog Distribution Manager (Catalog HUB) | FE | 10% | 30% | 50% | |||||||||
| BE | 10% | 30% | 50% | ||||||||||
| Catalog Subscription Manager (Catalog HUB) | FE | ||||||||||||
| BE | |||||||||||||
| Regular remote Shop (0%) | FE | Depends on SLH | |||||||||||
| BE |
Development tasks
This contains the tasks at the entire team. Each week contains these information according to the progess of the task:
- Phase 1: RFD Ready for Development
- Phase 2: In development --> Progress in %
- Phase 3: DEV testing - Developers finished development but are doing QA on their code
- Phase 4: QA testing - QA is having this on their table
- Phase 5: Fixing - QA returned with some flaws
- Phase 6: Code review - The code will be reviewed
- Phase 7: Done - Ready for deployment
- Phase 8: Working on feedback from client (initially unspecified additions, extensions)