RHB:Gleitender Durchschnitt
Revision as of 07:43, 27 September 2024 by Mathiashoeschen (talk | contribs)
Projektziele
Der Warenwert wird einstellbar berechnet nach:
- GLD
- Effektiver Einkaufspreis
- Verkaufspreis mit Preislistenauswahl
Deadlines
- Tests ab Mitte Oktober
Main building blocks
FI Settings Admin App
- Design Moqups (MH)
- Simple setting for GLD and eventually price list for sales pricelist based valuation
- Feedback-Session (RS with SS und SL)
- Develop (MH & SL)
Stock Intake Business Logic Service
One background service, which performs stock intake as SOS-RPC call. It offers methods for various stock intake scenarios.
ToDos
- Design and document methods and background service (SS)
- Implement
- Implement the Stocktake Business Logic Service (Chris)
- Find and replace stock intake methods with SOS-RPC calls.
- Develop (SL)
GLD Umschlagshäufigkeits-Auswertung für Abschreibungen
One report from Inventory, which helps the user for depreciation calculation, so that they can manually change the values. Is added to the App:Stocktaking app - see price entry screen
ToDos:
- add the download excel button to the screen
- Develop (SL)
Project plan
W-38
16.-20.09. |
W-39
23.-27.09. |
W-40
30.-04.10. |
W-41
07.-11.10. |
W-42
14.-18.10 |
W-43
20.-24.10 |
W-44
28.10-01.11 |
W-45
04.-08.11. |
W-46
11.-15.11. |
W-47
18.-22.11. | |
---|---|---|---|---|---|---|---|---|---|---|
Preparations | Preparation, Mockups, Process Definitions, ... | |||||||||
App:Product classification management | DEV | QA | Acceptance Tests | Buffer | ||||||
App:Approval strategies administration | DEV | QA | ||||||||
App:Task manager | DEV | |||||||||
Dev:Approval agent | DEV |
Relevent Events
ZS | RhB | Acceptance criterion | ||
---|---|---|---|---|
Sep | KW 36 | Vorbereitung der Mockups und Taskdefinitionen gesamtes Projekt | Mit SBB abgestimmt sein, beide Seiten haben das gleiche Verständnis was umgesetzt wird. | |
KW 37 | ||||
KW 38 | ||||
KW 39 | ||||
Okt | KW 40 | |||
KW 41 | ||||
KW 42 | ||||
KW 44 | ||||
Nov | KW 45 | |||
KW 46 | Finale Installation auf der WBW-INT 15.11.2024 | Finale Abnahmen | ||
KW 47 | Finale Installation auf der WBW-INT 19.11.2024 | Beginn der Schulung SBB 21.11.2024 | ||
KW 48 |