Development Planning 01.12. - 12.12.2025.
Revision as of 09:26, 16 December 2025 by Davorciric (talk | contribs)
Team availability
This map holds the ZUGSEIL product development team and its planned availability during the upcoming days. If anything changes to this availability, please notify the line and the product manager as soon as possible.
| Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Function | 01.12. | 02.12. | 03.12. | 04.12. | 05.12 | 08.12. | 09.12. | 10.12. | 11.12. | 12.12. | 15.12. | 16.12. | 17.12. | 18.12. | 19.12. | 22.12. | 23.12. | 24.12. | 25.12. | 26.12. |
| Stefan Seiler | Product Owner | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ | ❓ |
| Rene Schneider | Process Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ |
| Christiane Hornemann | UI Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Dennis Huesemann | Server administrator | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Davor Ciric | Senior Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ❌ | ✅ |
| Tijana Bezbradica | Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Luka Grbic | Support / QA | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Nikola Kerkez | Backend Developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Petar Ilic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Aleksandar Lazic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Zivko Rankovic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Ivan Juras | Backend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ |
| Nataša Lukić | Backend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Nebojsa Trajkovic | B-Op developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ | ❌ | ❌ | ❌ | ❌ | ❌ |
👨💻 For more detailed development HISTORY on weekly basis -> see this page
👨💻 For more detailed development SUPPORT planning -> see this page
Regular vacation requests are applied to over this page, please.
| TOPIC/Project
Task creation |
WBS / Project / Task | FE
BE |
06.10.-10.10. | 13.10.-17.10. | 20.10.-24.10. | 27.10.-31.10. | 03.11.-07.11. | 10.11.-14.11. | 17.11.-21.11. | 24.11.-28.11. | 01.12.-05.12. | 08.12.-12.12. | Promises / Customer Info / Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Regular Shop refactorization | FE | 20% | 20% | same what we did for Context based ordering, needs to be done for Regular (speed optimization) | |||||||||
| BE | 20% | 20% | |||||||||||
| SLH (to replace EBusinessCache) | 10% | ||||||||||||
| 🚀 SBB HYPERCARE (after GoLive) | FE | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Finalization | Done | Phase that comes after GoLive | |
| BE | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Ongoing | Finalization | Done | |||
| Design Studio extensions (for material and financial approvals) | FE | 30% | 100% | Done | Design Studio, Orders overview/details, Pending tasks app | ||||||||
| BE | 30% | 100% | Done | ||||||||||
| Catalog Designer (Catalog HUB) | FE | 30% | 60% | 80% | 80% | 90% | 90% | 90% | 90% | 90% | 90% | not 100% because Supplier catalogs are still missing | |
| BE | 30% | 60% | 80% | 80% | 90% | 90% | 90% | 90% | 90% | 90% | |||
| Catalog Distribution Manager (Catalog HUB) | FE | 10% | 30% | 50% | 70% | 90% | 90% | 90% | 90% | 90% | not 100% because of SLH | ||
| BE | 10% | 30% | 50% | 70% | 90% | 90% | 90% | 90% | 90% | ||||
| Catalog Subscription Manager (Catalog HUB) | FE | 20% | 30% | 60% | first DEMO with SBB on 16.12.2025. | ||||||||
| BE | 20% | 30% | 60% | ||||||||||
| Regular remote Shop (0%) | FE | Depends on SLH | |||||||||||
| BE |
Development tasks
This contains the tasks at the entire team. Each week contains these information according to the progess of the task:
- Phase 1: RFD Ready for Development
- Phase 2: In development --> Progress in %
- Phase 3: DEV testing - Developers finished development but are doing QA on their code
- Phase 4: QA testing - QA is having this on their table
- Phase 5: Fixing - QA returned with some flaws
- Phase 6: Code review - The code will be reviewed
- Phase 7: Done - Ready for deployment
- Phase 8: Working on feedback from client (initially unspecified additions, extensions)