Difference between revisions of "Development Sprint Planning 21.04 - 02.05"
Jump to navigation
Jump to search
Davorciric (talk | contribs) |
Davorciric (talk | contribs) |
||
| Line 195: | Line 195: | ||
!<u>Sprint-13</u> 31.03.-04.04. | !<u>Sprint-13</u> 31.03.-04.04. | ||
!<u>Sprint-14</u> 07.04.-11.04. | !<u>Sprint-14</u> 07.04.-11.04. | ||
!<u>Sprint-14</u> 14.04.-18.04. | |||
!<u>Sprint-15</u> 21.04.-25.04. | |||
!Promises / Customer Info / Comments | !Promises / Customer Info / Comments | ||
|- | |- | ||
| Line 204: | Line 206: | ||
|90% | |90% | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
| | |||
| | |||
| | | | ||
| rowspan="2" |Practically done, but there are feedback from client that are considered | | rowspan="2" |Practically done, but there are feedback from client that are considered | ||
| Line 213: | Line 217: | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
|- | |- | ||
| rowspan="2" |Staff based data ('''SBB''') | | rowspan="2" |Staff based data ('''SBB''') | ||
| Line 220: | Line 226: | ||
|50% | |50% | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 228: | Line 236: | ||
|50% | |50% | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 237: | Line 247: | ||
|10% | |10% | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 246: | Line 258: | ||
|30% | |30% | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 255: | Line 269: | ||
|30% | |30% | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 267: | Line 283: | ||
|90% | |90% | ||
|90% | |90% | ||
|90% | |||
| | |||
| rowspan="2" | | | rowspan="2" | | ||
|- | |- | ||
| Line 276: | Line 294: | ||
|90% | |90% | ||
|90% | |90% | ||
|90% | |||
| | |||
|- | |- | ||
|Abstract controller | |Abstract controller | ||
| Line 285: | Line 305: | ||
|40% | |40% | ||
|50% | |50% | ||
|60% | |||
| | |||
| | | | ||
|- | |- | ||
| Line 293: | Line 315: | ||
| | | | ||
|80% | |80% | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 298: | Line 322: | ||
|- | |- | ||
|BE | |BE | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 312: | Line 338: | ||
|10% | |10% | ||
|50% | |50% | ||
| | |||
| | |||
| rowspan="2" | | | rowspan="2" | | ||
|- | |- | ||
| | | | ||
|BE | |BE | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 325: | Line 355: | ||
| | | | ||
|FE | |FE | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 339: | Line 371: | ||
| | | | ||
|10% | |10% | ||
| | |||
| | |||
|- | |- | ||
| rowspan="2" |Catalogs (skinny version) | | rowspan="2" |Catalogs (skinny version) | ||
| | | | ||
|FE | |FE | ||
| | |||
| | |||
| | | | ||
| | | | ||
| Line 352: | Line 388: | ||
| | | | ||
|BE | |BE | ||
| | |||
| | |||
| | | | ||
| | | | ||
Revision as of 10:54, 23 April 2025
Team availability
This map holds the ZUGSEIL product development team and its planned availability during the upcoming days. If anything changes to this availability, please notify the line and the product manager as soon as possible.
| Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | ||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Function | 21.04 | 22.04 | 23.04 | 24.04 | 25.04 | 28.04 | 29.04 | 30.04 | 01.05 | 02.05 |
| Stefan Seiler | Product Owner | ❌ | ❌ | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Rene Schneider | Process Quality Manager | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Christiane Hornemann | UI Quality Manager | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Davor Ciric | Senior Delivery Manager | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Tijana Bezbradica | Delivery Manager | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Ilija Bubanj | Quality Engineer | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Nikola Kerkez | Backend Developer | ❌ | ❌ | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Petar Ilic | Frontend developer | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Aleksandar Lazic | Frontend developer | ❌ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ |
| Zivko Rankovic | Frontend developer | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
| Ivan Juras | Backend developer | ❌ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ |
| Nebojsa Trajkovic | B-Op developer | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ |
Regular vacation requests are applied to over this page, please.
| TOPIC/Project
Task creation |
WBS / Project | FE
BE |
Sprint-12 10.03.-14.03. | Sprint-12 17.03.-21.03. | Sprint-13 24.03.-28.03. | Sprint-13 31.03.-04.04. | Sprint-14 07.04.-11.04. | Sprint-14 14.04.-18.04. | Sprint-15 21.04.-25.04. | Promises / Customer Info / Comments |
|---|---|---|---|---|---|---|---|---|---|---|
| Orders overview app (responsive) (SBB) | FE | 70% | QA testing | 90% | QA testing | Practically done, but there are feedback from client that are considered | ||||
| BE | 80% | QA testing | 90% | QA testing | Done | |||||
| Staff based data (SBB) | FE | 50% | Done | |||||||
| BE | 50% | Done | ||||||||
| SOS to newest CoreClient | BE | 10% | Done | |||||||
| Export/import products (Classifications and catalog extensions) (KOR) | FE | 30% | Done | |||||||
| BE | 30% | Done | ||||||||
| Pick up manager: Manipulate shipments extension (AUA) | FE | 90% | 90% | 90% | 90% | 90% | 90% | |||
| BE | 90% | 90% | 90% | 90% | 90% | 90% | ||||
| Abstract controller | BE | 30% | 40% | 50% | 60% | |||||
| Appointments (responsive) | FE | 80% | ||||||||
| BE | ||||||||||
| Regular shop - responsive (SBB) | FE | 10% | 50% | |||||||
| BE | ||||||||||
| Remote regular shopping | FE | |||||||||
| BE | 10% | |||||||||
| Catalogs (skinny version) | FE | |||||||||
| BE |
Development tasks
This contains the tasks at the entire team. Each week contains these information according to the progess of the task:
- Phase 1: RFD Ready for Development
- Phase 2: In development --> Progress in %
- Phase 3: DEV testing - Developers finished development but are doing QA on their code
- Phase 4: QA testing - QA is having this on their table
- Phase 5: Fixing - QA returned with some flaws
- Phase 6: Code review - The code will be reviewed
- Phase 7: Done - Ready for deployment
- Phase 8: Working on feedback from client (initially unspecified additions, extensions)