Difference between revisions of "Development Sprint Planning 19.05 - 30.05"
Jump to navigation
Jump to search
Davorciric (talk | contribs) |
Davorciric (talk | contribs) |
||
| (5 intermediate revisions by the same user not shown) | |||
| Line 333: | Line 333: | ||
|'''Nikola Kerkez''' | |'''Nikola Kerkez''' | ||
|BE | |BE | ||
| | |60% Appointments, | ||
| | 40% Pick up manager (22.05/23.05) | ||
|<s>Nikola and Stefan on SLH (3 working days)</s> | |||
60% Pick up manager (3 working days), underestimated and took longer | |||
|- | |- | ||
|'''Ivan Juras''' | |'''Ivan Juras''' | ||
|BE | |BE | ||
|Abstract controller | |100% Abstract controller | ||
| | |100% Abstract controller | ||
|- | |- | ||
|'''Aleksandar Lazic''' | |'''Aleksandar Lazic''' | ||
| FE | | FE | ||
|Storybook FE components | |100% Storybook FE components | ||
| | |40% Pick up manager, 60% Storybook | ||
|- | |- | ||
|'''Živko Rankovic''' | |'''Živko Rankovic''' | ||
|FE | |FE | ||
|100% Returns responsive | |100% Returns responsive | ||
| | |100% Returns responsive | ||
|- | |- | ||
|'''Petar Ilic''' | |'''Petar Ilic''' | ||
|FE | |FE | ||
|100% Appointments responsive + FE urgent tasks | |100% Appointments responsive + FE urgent tasks | ||
| | |Orders overview internal feedback | ||
|}Regular vacation requests are [https://wiki.zugseil.com/en/index.php/Dev:ZUGSEIL_Product_Development_Team_Vacations applied to over this page], please. | |}Regular vacation requests are [https://wiki.zugseil.com/en/index.php/Dev:ZUGSEIL_Product_Development_Team_Vacations applied to over this page], please. | ||
{| class="wikitable" | {| class="wikitable" | ||
| Line 371: | Line 373: | ||
!<u>Sprint-16</u>12.05.-16.05. | !<u>Sprint-16</u>12.05.-16.05. | ||
!<u>Sprint-17</u> 19.05.-23.05. | !<u>Sprint-17</u> 19.05.-23.05. | ||
!<u>Sprint-17</u> 12.05.-30.05. | |||
!Promises / Customer Info / Comments | !Promises / Customer Info / Comments | ||
! | ! | ||
| Line 380: | Line 383: | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 393: | Line 397: | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 405: | Line 410: | ||
|FE | |FE | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 418: | Line 424: | ||
|BE | |BE | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 432: | Line 439: | ||
|BE | |BE | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 454: | Line 462: | ||
|⚠️ must be planned <s>this</s> for next week. | |⚠️ must be planned <s>this</s> for next week. | ||
|⚠️ must be planned <s>this</s> for next week. Postponed again | |⚠️ must be planned <s>this</s> for next week. Postponed again | ||
| | |100% | ||
|{{Red-Tag|RedText=Fixing}} | |||
| | | | ||
| | | | ||
| Line 467: | Line 476: | ||
|90% | |90% | ||
| | | | ||
| | |100% | ||
|{{Red-Tag|RedText=Fixing}} | |||
| | | | ||
| | | | ||
| Line 482: | Line 492: | ||
|65% | |65% | ||
|75% | |75% | ||
| | |80% | ||
|85% | |||
|progress is very slow because of the changes during development | |progress is very slow because of the changes during development | ||
| | | | ||
| Line 497: | Line 508: | ||
| | | | ||
| | | | ||
| | |90% | ||
|90% | |||
| rowspan="2" |Waiting for the abstract controller | | rowspan="2" |Waiting for the abstract controller | ||
| | | | ||
| Line 510: | Line 522: | ||
|86% | |86% | ||
|87% | |87% | ||
| | |90% | ||
|90% | |||
| | | | ||
|- | |- | ||
| Line 522: | Line 535: | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 535: | Line 549: | ||
|{{Yellow-Tag|Text=QA testing}} | |{{Yellow-Tag|Text=QA testing}} | ||
|{{Green-Tag|Text=Done}} | |{{Green-Tag|Text=Done}} | ||
| | |||
| | | | ||
| | | | ||
| Line 552: | Line 567: | ||
| | | | ||
| | | | ||
|30% | |||
| rowspan="2" |Depends on the abstract controller | | rowspan="2" |Depends on the abstract controller | ||
| | | | ||
|- | |- | ||
|BE | |BE | ||
| | |||
| | | | ||
| | | | ||
| Line 570: | Line 587: | ||
| rowspan="2" | | | rowspan="2" | | ||
|FE | |FE | ||
| | |||
| | | | ||
| | | | ||
| Line 583: | Line 601: | ||
|- | |- | ||
|BE | |BE | ||
| | |||
| | | | ||
| | | | ||
| Line 597: | Line 616: | ||
| rowspan="2" | | | rowspan="2" | | ||
|FE | |FE | ||
| | |||
| | | | ||
| | | | ||
| Line 610: | Line 630: | ||
|- | |- | ||
|BE | |BE | ||
| | |||
| | | | ||
| | | | ||
Latest revision as of 09:07, 30 May 2025
Team availability
This map holds the ZUGSEIL product development team and its planned availability during the upcoming days. If anything changes to this availability, please notify the line and the product manager as soon as possible.
| Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | Mon | Tue | Wed | Thu | Fri | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Function | 19.05 | 20.05 | 21.05 | 22.05 | 23.05 | 26.05 | 27.05 | 28.05 | 29.05 | 30.05 | 02.06. | 03.06. | 04.06. | 05.06. | 06.06. | 09.06. | 10.06. | 11.06. | 12.06. | 13.06. |
| Stefan Seiler | Product Owner | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Rene Schneider | Process Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Christiane Hornemann | UI Quality Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Davor Ciric | Senior Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Tijana Bezbradica | Delivery Manager | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Ilija Bubanj | Quality Engineer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Nikola Kerkez | Backend Developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Petar Ilic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Aleksandar Lazic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Zivko Rankovic | Frontend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Ivan Juras | Backend developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ |
| Nebojsa Trajkovic | B-Op developer | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ✅ | ❌ | ✅ | ✅ | ✅ | ❌ | ❌ | ❌ | ❌ | ❌ | ✅ |
| 👨💻 DEV assignments | 19.05. - 23.05.2025. | 26.05. - 30.05.2025. | |
|---|---|---|---|
| Nikola Kerkez | BE | 60% Appointments,
40% Pick up manager (22.05/23.05) |
60% Pick up manager (3 working days), underestimated and took longer |
| Ivan Juras | BE | 100% Abstract controller | 100% Abstract controller |
| Aleksandar Lazic | FE | 100% Storybook FE components | 40% Pick up manager, 60% Storybook |
| Živko Rankovic | FE | 100% Returns responsive | 100% Returns responsive |
| Petar Ilic | FE | 100% Appointments responsive + FE urgent tasks | Orders overview internal feedback |
Regular vacation requests are applied to over this page, please.
| TOPIC/Project
Task creation |
WBS / Project / Task | FE
BE |
Sprint-13 24.03.-28.03. | Sprint-13 31.03.-04.04. | Sprint-14 07.04.-11.04. | Sprint-14 14.04.-18.04. | Sprint-15 21.04.-25.04. | Sprint-15 28.04.-02.05. | Sprint-16 05.05.-09.05. | Sprint-1612.05.-16.05. | Sprint-17 19.05.-23.05. | Sprint-17 12.05.-30.05. | Promises / Customer Info / Comments | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Orders overview app (responsive) (SBB) | FE | 90% | QA testing | Done | ||||||||||
| BE | 90% | QA testing | Done | |||||||||||
| Staff based data (SBB) | FE | Done | ||||||||||||
| BE | Done | |||||||||||||
| SOS to newest CoreClient | BE | Done | ||||||||||||
| Pick up manager: Manipulate shipments extension (AUA) | FE | 90% | 90% | 90% | 90% | 90% | 90% | ⚠️ must be planned |
⚠️ must be planned |
100% | Fixing | |||
| BE | 90% | 90% | 90% | 90% | 90% | 90% | 90% | 100% | Fixing | |||||
| Abstract controller | BE | 30% | 40% | 50% | 60% | Nikola Vacation | 60% | 65% | 75% | 80% | 85% | progress is very slow because of the changes during development | ||
| Appointments (responsive) | FE | 80% | 90% | 90% | Waiting for the abstract controller | |||||||||
| BE | 80% | 81% | 82% | 83% | 84% | 85% | 86% | 87% | 90% | 90% | ||||
| Regular shop - responsive (SBB) | FE | 10% | 50% | 80% | QA testing | Done | ||||||||
| BE | QA testing | Done | ||||||||||||
| EMA remote shop | FE | 30% | Depends on the abstract controller | |||||||||||
| BE | ||||||||||||||
| Regular remote shopping | FE | Depends on the abstract controller | ||||||||||||
| BE | ||||||||||||||
| Catalogs Designer (skinny version) | FE | Not even started | ||||||||||||
| BE |
Development tasks
This contains the tasks at the entire team. Each week contains these information according to the progess of the task:
- Phase 1: RFD Ready for Development
- Phase 2: In development --> Progress in %
- Phase 3: DEV testing - Developers finished development but are doing QA on their code
- Phase 4: QA testing - QA is having this on their table
- Phase 5: Fixing - QA returned with some flaws
- Phase 6: Code review - The code will be reviewed
- Phase 7: Done - Ready for deployment
- Phase 8: Working on feedback from client (initially unspecified additions, extensions)